I am trying to create a formula that will result in a date. I have a start
date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#2
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
You could use the Workday function.
In A1, enter the first Friday of 2007 (or whatever year you need) 1/5/07 In A2, enter =A1+7, then copy down as far as needed (my example is in A1:A52). Then with your start date in B1 and number of days in B2, enter =WORKDAY(B1,B2,A1:A52) "tamarade" wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#3
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
A couple of suggestions
Try Workday and define a list of all the fridays and holidays this allows you to consider holidays as well if this is applicable. If this function is not available, and returns the #NAME? error, install and load the Analysis ToolPak add-in. Otherwise try =A3+INT((B3-1)/4)*7+MOD(B3-1,4) +IF(OR(WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)<WEEKDAY(A3,2), WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)4),3,0) It is a bit of a mouthfull but it works. It is probably easier to use a macro function as follows, this needs to be pasted in a module for the workbook: Option Explicit Function networkingdays4dayweek(ByVal startdate As Date, ByVal days As Integer) As Date Dim d As Date ' working date Dim w As Integer ' whole week days Dim dd As Integer ' remaining days Dim ewd As Integer ' end weekday no. Dim swd As Integer ' start weekday no. Application.Volatile d = startdate swd = Weekday(d, vbMonday) If swd 4 Then ' not a working day networkingdays4dayweek = 0 Exit Function End If w = Int((days - 1) / 4) * 7 dd = (days - 1) Mod 4 d = d + w + dd ' end date before adjustment ewd = Weekday(d, vbMonday) ' check if needs adjustment ' ie falls before the start date or after Thursday If (ewd < swd Or ewd 4) Then d = d + 3 End If networkingdays4dayweek = d End Function and just call it in the sheet with =networkingdays4dayweek(A3,B3) -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "tamarade" wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#4
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Hi
Some time ago I created an equivalent to WORKDAYS excel function (EnchWorkaysN()), which allows you to count workdays between 2 dates. To have it work, you have to copy another 3 functions into your VBA module too. =ENCHWORKDAYS(Date1,Date2,[Holidays],[Weekends],[Weekstart]) , where Date1 and Date2 are start and end dates; Holidays is a holiday list (a range reference or an array or a single date) Weekends is a weekend days (1-7) list (a range reference or an array or single number) Weekstart redefines 1st day of week for weekends count (1 - sunday, 2 - monday, etc.) You need a similar equivalent of NETWORKDAYS function for your task. Maybe you can use my code as start point. ------------------------------------------- Option Base 1 Function SelectionSort(TempArray As Variant) Dim MaxVal As Variant Dim MaxIndex As Integer Dim i, j As Integer ' The function sorts all entries in 1-dimensional array, ' it's a function provided in Microsoft KB article 133135 ' Step through the elements in the array starting with the ' last element in the array. For i = UBound(TempArray) To 1 Step -1 ' Set MaxVal to the element in the array and save the ' index of this element as MaxIndex. MaxVal = TempArray(i) MaxIndex = i ' Loop through the remaining elements to see if any is ' larger than MaxVal. If it is then set this element ' to be the new MaxVal. For j = 1 To i If TempArray(j) MaxVal Then MaxVal = TempArray(j) MaxIndex = j End If Next j ' If the index of the largest element is not i, then ' exchange this element with element i. If MaxIndex < i Then TempArray(MaxIndex) = TempArray(i) TempArray(i) = MaxVal End If Next i End Function Function SelectionUnique(TempArray As Variant, Optional AllowZeros As Boolean = True) Dim MaxVal, TempArray2() As Variant Dim MaxIndex As Integer Dim i, j As Integer ' The function is meant to work with ordered arrays ' and removes all double entries and Null values ' (Except when the is the only value, and it is Null). ' Optional argument determines, how 0 values are processed ' Initialize j = 1 ReDim TempArray2(1 To j) As Variant TempArray2(1) = Null ' Step through the elements in the array starting with the ' first element in the array. For i = 1 To UBound(TempArray) Step 1 If IsNull(TempArray(i)) Or _ IsEmpty(TempArray(i)) Or _ (TempArray(i) = 0 And AllowZeros = False) Then Else ' Redim TempArray2 and add an element ReDim Preserve TempArray2(1 To j) As Variant TempArray2(j) = TempArray(i) j = j + 1 ' Set CurrVal to the element in the array currval = TempArray(i) ' Cycle through next elements until value changes k = 0 If i < UBound(TempArray) Then Do While TempArray(i + k + 1) = currval k = k + 1 If i + k UBound(TempArray) Then Exit Do Loop End If i = Application.WorksheetFunction.Max(i, i + k - 1) End If Next i ' Write the passed array over TempArray = TempArray2 End Function Function SelectionToInteger(TempArray As Variant) Dim i As Integer ' The function cuts off decimal part from all non-empty elements of array ' Step through the elements in the array starting with the ' first element in the array. For i = 1 To UBound(TempArray) Step 1 If IsNull(TempArray(i)) Then Else ' Replace array element with it's integer value TempArray(i) = Int(TempArray(i)) End If Next i End Function ' NB! The function starts here!!! Public Function EnchWorkdaysN(StartDate As Date, _ EndDate As Date, _ Optional Holidays As Variant = Nothing, _ Optional Weekends As Variant = Nothing, _ Optional WeekStart As Integer = 1) Dim arrayH As Variant, arrayW As Variant Dim di As Date, dn As Date, dx As Date ' The result doesn't depend on order of values of first 2 parameters. ' When parameter Holidays is omitted, or Null, or not a positive numeric (date) value, ' or not an array or cell range with numeric values, then no holidays ' are left out from day's count. ' When parameter Weekends is omitted, or Null, or not a numeric value =1 and <8, ' or not an array or cell range with at least one numeric value between =1 and <8, ' then 1 and 7 (Saturday and Sunday) are set for Weekend default walues, ' and according weekdays are left out from day's count. ' No weekends are left out from day's count (7-workday week) only then, ' when fourth parameter is set to FALSE. ' The parameter WeekStart determines, how are determined weekends in 4th parameter ' Allowed values for parameter WeekStart are integers 1 to 7. ' The number 1 indicates Sunday as 1st day of week, ' the number 2 indicates Monday as first day of week, etc. ' When the parameter WeekStart is not between 1 and 7, then WeekStart = (Abs(WeekStart) Mod 7)+1 ' Initialize ArrayH If TypeName(Holidays) = "Variant()" Then ReDim arrayH(1 To UBound(Holidays)) As Variant For i = 1 To UBound(Holidays) arrayH(i) = IIf(VarType(Holidays(i, 1)) 0 And VarType(Holidays(i, 1)) < 8, Holidays(i, 1), Null) arrayH(i) = IIf(arrayH(i) < 0, Null, arrayH(i)) Next i ElseIf (VarType(Holidays) = 8192 And VarType(Holidays) <= 8199) Or _ VarType(Holidays) = 8204 Then ReDim arrayH(1 To UBound(Holidays.Value)) As Variant For i = 1 To UBound(Holidays.Value) arrayH(i) = IIf(VarType(Holidays(i)) 0 And VarType(Holidays(i)) < 8, Holidays(i), Null) arrayH(i) = IIf(arrayH(i) < 0, Null, arrayH(i)) Next i ElseIf VarType(Holidays) < 8 Then ReDim arrayH(1) As Variant arrayH(1) = Holidays arrayH(1) = IIf(arrayH(1) < 0, Null, arrayH(1)) Else ReDim arrayH(1) As Variant arrayH(1) = Null End If ' Sort arrayH SelectionSort arrayH ' Replace non-integer values with integers SelectionToInteger arrayH ' Remove double entries and empty elements SelectionUnique arrayH ' Initialize arrayW If VarType(Weekends) < 11 Then If TypeName(Weekends) = "Nothing" Then ReDim arrayW(1 To 2) As Variant arrayW(1) = 1 arrayW(2) = 7 ElseIf TypeName(Weekends) = "Variant()" Then ReDim arrayW(1 To UBound(Weekends)) As Variant For i = 1 To UBound(Weekends) If UBound(Weekends) = 1 Then arrayW(i) = IIf(VarType(Weekends(i)) 0 And VarType(Weekends(i)) < 8, ((Abs(Weekends(i)) + 12 + WeekStart) Mod 7) + 1, Null) Else arrayW(i) = IIf(VarType(Weekends(i, 1)) 0 And VarType(Weekends(i, 1)) < 8, ((Abs(Weekends(i, 1)) + 12 + WeekStart) Mod 7) + 1, Null) End If arrayW(i) = IIf(arrayW(i) < 1 Or arrayW(i) = 8, Null, arrayW(i)) Next i ElseIf VarType(Weekends) = 8192 And VarType(Weekends) <= 8199 Or _ VarType(Weekends) = 8204 Then ReDim arrayW(1 To UBound(Weekends.Value)) As Variant For i = 1 To UBound(Weekends.Value) arrayW(i) = IIf(VarType(Weekends(i)) 0 And VarType(Weekends(i)) < 8, ((Abs(Weekends(i)) + 12 + WeekStart) Mod 7) + 1, Null) arrayW(i) = IIf(arrayW(i) < 1 Or arrayW(i) = 8, Null, arrayW(i)) Next i ElseIf (Int(Weekends) = 1 And Int(Weekends) < 8) Then ReDim arrayW(1) As Variant arrayW(1) = ((Abs(Weekends) + 12 + WeekStart) Mod 7) + 1 arrayW(1) = IIf(arrayW(1) < 1 Or arrayW(1) = 8, Null, arrayW(1)) Else ReDim arrayW(1 To 2) As Variant arrayW(1) = 1 arrayW(2) = 7 End If ' Sort arrayW SelectionSort arrayW ' Replace non-integer values with integers SelectionToInteger arrayW ' Remove double entries and empty elements SelectionUnique arrayW, False Else ' Set 1st element to 0 for 7-workday week ReDim arrayW(1) As Variant arrayW(1) = IIf(Weekends = False, 0, Null) End If ' When empty array, insert default values If arrayW(1) = Null Then ReDim arrayW(1 To 2, 1) As Variant arrayW(1) = 1 arrayW(2) = 7 End If ' Calculate the number of workdays in date interval determined by StartDay and EndDay EnchWorkdaysN = 0 di = Application.WorksheetFunction.Min(StartDate, EndDate) dn = Application.WorksheetFunction.Max(StartDate, EndDate) dx = di Do While dx <= dn x = False i = 1 Do While x = False And i <= UBound(arrayH) And TypeName(arrayH(1)) < "Null" x = (dx = arrayH(i)) i = i + 1 Loop i = 1 Do While x = False And i <= UBound(arrayW) And arrayW(1) < 0 x = (Weekday(dx) = arrayW(i)) i = i + 1 Loop If Not (x) Then EnchWorkdaysN = EnchWorkdaysN + 1 dx = dx + 1 Loop End Function -- Arvi Laanemets ( My real mail address: arvi.laanemets<attarkon.ee ) "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#5
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Hi
Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#6
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Roger,
That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#7
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Thank you, Martin.
Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#8
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Unless I'm missing something, I can't get Rogers or Martins formulas to
work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#9
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
On Mon, 8 Jan 2007 19:10:01 -0800, tamarade
wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? Here is a UDF that should do what you want. It's use is similar to the WORKDAY function except you can define up to four "weekend" days. To enter the UDF, <alt-F11 opens the VB Editor. Ensure your project is highlighted in the Project Explorer window, then Insert/Module and paste the code below into the window that opens. To use this UDF, enter a formula of the type: =wrkday(start_date,num_days,holidays,1,6,7) ======================================= Function NWrkDays(StartDate As Date, EndDate As Date, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Long ' Sunday = 1; Monday = 2; ... Saturday = 7 'credits to Myrna Dim i As Long Dim Count As Long Dim H As Variant Dim w As Long Dim SD As Date, ED As Date Dim DoHolidays As Boolean Dim NegCount As Boolean DoHolidays = Not (Holidays Is Nothing) SD = StartDate: ED = EndDate If SD ED Then SD = EndDate: ED = StartDate NegCount = True End If w = Weekday(SD - 1) For i = SD To ED Count = Count + 1 w = (w Mod 7) + 1 Select Case w Case WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4 Count = Count - 1 Case Else If DoHolidays Then If IsNumeric(Application.Match(i, Holidays, 0)) Then _ Count = Count - 1 End If End Select Next i If NegCount = True Then Count = -Count NWrkDays = Count End Function Function WrkDay(StartDate As Date, ByVal NumDays As Long, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Date ' Sunday = 1; Monday = 2; ... Saturday = 7 Dim i As Long Dim TempDate As Date Dim Stp As Integer Dim NonWrkDays As Long Dim temp As Long, SD As Date, ED As Date Stp = Sgn(NumDays) 'Add NumDays TempDate = StartDate + NumDays 'Add Non-Workdays Do While Abs(NumDays) < temp SD = Application.WorksheetFunction.Min(StartDate + Stp, TempDate) ED = Application.WorksheetFunction.Max(StartDate + Stp, TempDate) temp = NWrkDays(SD, ED, Holidays, WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4) TempDate = TempDate + NumDays - Stp * (temp) Loop WrkDay = TempDate End Function ============================================ --ron |
#10
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Works good, Ron!
I'd still like a worksheet function if ya got one! Biff "Ron Rosenfeld" wrote in message ... On Mon, 8 Jan 2007 19:10:01 -0800, tamarade wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? Here is a UDF that should do what you want. It's use is similar to the WORKDAY function except you can define up to four "weekend" days. To enter the UDF, <alt-F11 opens the VB Editor. Ensure your project is highlighted in the Project Explorer window, then Insert/Module and paste the code below into the window that opens. To use this UDF, enter a formula of the type: =wrkday(start_date,num_days,holidays,1,6,7) ======================================= Function NWrkDays(StartDate As Date, EndDate As Date, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Long ' Sunday = 1; Monday = 2; ... Saturday = 7 'credits to Myrna Dim i As Long Dim Count As Long Dim H As Variant Dim w As Long Dim SD As Date, ED As Date Dim DoHolidays As Boolean Dim NegCount As Boolean DoHolidays = Not (Holidays Is Nothing) SD = StartDate: ED = EndDate If SD ED Then SD = EndDate: ED = StartDate NegCount = True End If w = Weekday(SD - 1) For i = SD To ED Count = Count + 1 w = (w Mod 7) + 1 Select Case w Case WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4 Count = Count - 1 Case Else If DoHolidays Then If IsNumeric(Application.Match(i, Holidays, 0)) Then _ Count = Count - 1 End If End Select Next i If NegCount = True Then Count = -Count NWrkDays = Count End Function Function WrkDay(StartDate As Date, ByVal NumDays As Long, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Date ' Sunday = 1; Monday = 2; ... Saturday = 7 Dim i As Long Dim TempDate As Date Dim Stp As Integer Dim NonWrkDays As Long Dim temp As Long, SD As Date, ED As Date Stp = Sgn(NumDays) 'Add NumDays TempDate = StartDate + NumDays 'Add Non-Workdays Do While Abs(NumDays) < temp SD = Application.WorksheetFunction.Min(StartDate + Stp, TempDate) ED = Application.WorksheetFunction.Max(StartDate + Stp, TempDate) temp = NWrkDays(SD, ED, Holidays, WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4) TempDate = TempDate + NumDays - Stp * (temp) Loop WrkDay = TempDate End Function ============================================ --ron |
#11
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
On Tue, 9 Jan 2007 21:50:02 -0500, "T. Valko" wrote:
Works good, Ron! I'd still like a worksheet function if ya got one! Biff I believe Bob Philips has posted a worksheet function solution. But for stuff like this, I find UDF's easier to implement and maintain. --ron |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Reusing formula | Excel Discussion (Misc queries) | |||
formula problem | Excel Worksheet Functions | |||
Wrong Week number | Excel Worksheet Functions | |||
Work Rota - Do I need a formula? | Excel Discussion (Misc queries) | |||
4 Day Work Week in a formula | Excel Discussion (Misc queries) |