#1
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
I am trying to create a formula that will result in a date. I have a start
date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#2
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
You could use the Workday function.
In A1, enter the first Friday of 2007 (or whatever year you need) 1/5/07 In A2, enter =A1+7, then copy down as far as needed (my example is in A1:A52). Then with your start date in B1 and number of days in B2, enter =WORKDAY(B1,B2,A1:A52) "tamarade" wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#3
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
A couple of suggestions
Try Workday and define a list of all the fridays and holidays this allows you to consider holidays as well if this is applicable. If this function is not available, and returns the #NAME? error, install and load the Analysis ToolPak add-in. Otherwise try =A3+INT((B3-1)/4)*7+MOD(B3-1,4) +IF(OR(WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)<WEEKDAY(A3,2), WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)4),3,0) It is a bit of a mouthfull but it works. It is probably easier to use a macro function as follows, this needs to be pasted in a module for the workbook: Option Explicit Function networkingdays4dayweek(ByVal startdate As Date, ByVal days As Integer) As Date Dim d As Date ' working date Dim w As Integer ' whole week days Dim dd As Integer ' remaining days Dim ewd As Integer ' end weekday no. Dim swd As Integer ' start weekday no. Application.Volatile d = startdate swd = Weekday(d, vbMonday) If swd 4 Then ' not a working day networkingdays4dayweek = 0 Exit Function End If w = Int((days - 1) / 4) * 7 dd = (days - 1) Mod 4 d = d + w + dd ' end date before adjustment ewd = Weekday(d, vbMonday) ' check if needs adjustment ' ie falls before the start date or after Thursday If (ewd < swd Or ewd 4) Then d = d + 3 End If networkingdays4dayweek = d End Function and just call it in the sheet with =networkingdays4dayweek(A3,B3) -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "tamarade" wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#4
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Hi
Some time ago I created an equivalent to WORKDAYS excel function (EnchWorkaysN()), which allows you to count workdays between 2 dates. To have it work, you have to copy another 3 functions into your VBA module too. =ENCHWORKDAYS(Date1,Date2,[Holidays],[Weekends],[Weekstart]) , where Date1 and Date2 are start and end dates; Holidays is a holiday list (a range reference or an array or a single date) Weekends is a weekend days (1-7) list (a range reference or an array or single number) Weekstart redefines 1st day of week for weekends count (1 - sunday, 2 - monday, etc.) You need a similar equivalent of NETWORKDAYS function for your task. Maybe you can use my code as start point. ------------------------------------------- Option Base 1 Function SelectionSort(TempArray As Variant) Dim MaxVal As Variant Dim MaxIndex As Integer Dim i, j As Integer ' The function sorts all entries in 1-dimensional array, ' it's a function provided in Microsoft KB article 133135 ' Step through the elements in the array starting with the ' last element in the array. For i = UBound(TempArray) To 1 Step -1 ' Set MaxVal to the element in the array and save the ' index of this element as MaxIndex. MaxVal = TempArray(i) MaxIndex = i ' Loop through the remaining elements to see if any is ' larger than MaxVal. If it is then set this element ' to be the new MaxVal. For j = 1 To i If TempArray(j) MaxVal Then MaxVal = TempArray(j) MaxIndex = j End If Next j ' If the index of the largest element is not i, then ' exchange this element with element i. If MaxIndex < i Then TempArray(MaxIndex) = TempArray(i) TempArray(i) = MaxVal End If Next i End Function Function SelectionUnique(TempArray As Variant, Optional AllowZeros As Boolean = True) Dim MaxVal, TempArray2() As Variant Dim MaxIndex As Integer Dim i, j As Integer ' The function is meant to work with ordered arrays ' and removes all double entries and Null values ' (Except when the is the only value, and it is Null). ' Optional argument determines, how 0 values are processed ' Initialize j = 1 ReDim TempArray2(1 To j) As Variant TempArray2(1) = Null ' Step through the elements in the array starting with the ' first element in the array. For i = 1 To UBound(TempArray) Step 1 If IsNull(TempArray(i)) Or _ IsEmpty(TempArray(i)) Or _ (TempArray(i) = 0 And AllowZeros = False) Then Else ' Redim TempArray2 and add an element ReDim Preserve TempArray2(1 To j) As Variant TempArray2(j) = TempArray(i) j = j + 1 ' Set CurrVal to the element in the array currval = TempArray(i) ' Cycle through next elements until value changes k = 0 If i < UBound(TempArray) Then Do While TempArray(i + k + 1) = currval k = k + 1 If i + k UBound(TempArray) Then Exit Do Loop End If i = Application.WorksheetFunction.Max(i, i + k - 1) End If Next i ' Write the passed array over TempArray = TempArray2 End Function Function SelectionToInteger(TempArray As Variant) Dim i As Integer ' The function cuts off decimal part from all non-empty elements of array ' Step through the elements in the array starting with the ' first element in the array. For i = 1 To UBound(TempArray) Step 1 If IsNull(TempArray(i)) Then Else ' Replace array element with it's integer value TempArray(i) = Int(TempArray(i)) End If Next i End Function ' NB! The function starts here!!! Public Function EnchWorkdaysN(StartDate As Date, _ EndDate As Date, _ Optional Holidays As Variant = Nothing, _ Optional Weekends As Variant = Nothing, _ Optional WeekStart As Integer = 1) Dim arrayH As Variant, arrayW As Variant Dim di As Date, dn As Date, dx As Date ' The result doesn't depend on order of values of first 2 parameters. ' When parameter Holidays is omitted, or Null, or not a positive numeric (date) value, ' or not an array or cell range with numeric values, then no holidays ' are left out from day's count. ' When parameter Weekends is omitted, or Null, or not a numeric value =1 and <8, ' or not an array or cell range with at least one numeric value between =1 and <8, ' then 1 and 7 (Saturday and Sunday) are set for Weekend default walues, ' and according weekdays are left out from day's count. ' No weekends are left out from day's count (7-workday week) only then, ' when fourth parameter is set to FALSE. ' The parameter WeekStart determines, how are determined weekends in 4th parameter ' Allowed values for parameter WeekStart are integers 1 to 7. ' The number 1 indicates Sunday as 1st day of week, ' the number 2 indicates Monday as first day of week, etc. ' When the parameter WeekStart is not between 1 and 7, then WeekStart = (Abs(WeekStart) Mod 7)+1 ' Initialize ArrayH If TypeName(Holidays) = "Variant()" Then ReDim arrayH(1 To UBound(Holidays)) As Variant For i = 1 To UBound(Holidays) arrayH(i) = IIf(VarType(Holidays(i, 1)) 0 And VarType(Holidays(i, 1)) < 8, Holidays(i, 1), Null) arrayH(i) = IIf(arrayH(i) < 0, Null, arrayH(i)) Next i ElseIf (VarType(Holidays) = 8192 And VarType(Holidays) <= 8199) Or _ VarType(Holidays) = 8204 Then ReDim arrayH(1 To UBound(Holidays.Value)) As Variant For i = 1 To UBound(Holidays.Value) arrayH(i) = IIf(VarType(Holidays(i)) 0 And VarType(Holidays(i)) < 8, Holidays(i), Null) arrayH(i) = IIf(arrayH(i) < 0, Null, arrayH(i)) Next i ElseIf VarType(Holidays) < 8 Then ReDim arrayH(1) As Variant arrayH(1) = Holidays arrayH(1) = IIf(arrayH(1) < 0, Null, arrayH(1)) Else ReDim arrayH(1) As Variant arrayH(1) = Null End If ' Sort arrayH SelectionSort arrayH ' Replace non-integer values with integers SelectionToInteger arrayH ' Remove double entries and empty elements SelectionUnique arrayH ' Initialize arrayW If VarType(Weekends) < 11 Then If TypeName(Weekends) = "Nothing" Then ReDim arrayW(1 To 2) As Variant arrayW(1) = 1 arrayW(2) = 7 ElseIf TypeName(Weekends) = "Variant()" Then ReDim arrayW(1 To UBound(Weekends)) As Variant For i = 1 To UBound(Weekends) If UBound(Weekends) = 1 Then arrayW(i) = IIf(VarType(Weekends(i)) 0 And VarType(Weekends(i)) < 8, ((Abs(Weekends(i)) + 12 + WeekStart) Mod 7) + 1, Null) Else arrayW(i) = IIf(VarType(Weekends(i, 1)) 0 And VarType(Weekends(i, 1)) < 8, ((Abs(Weekends(i, 1)) + 12 + WeekStart) Mod 7) + 1, Null) End If arrayW(i) = IIf(arrayW(i) < 1 Or arrayW(i) = 8, Null, arrayW(i)) Next i ElseIf VarType(Weekends) = 8192 And VarType(Weekends) <= 8199 Or _ VarType(Weekends) = 8204 Then ReDim arrayW(1 To UBound(Weekends.Value)) As Variant For i = 1 To UBound(Weekends.Value) arrayW(i) = IIf(VarType(Weekends(i)) 0 And VarType(Weekends(i)) < 8, ((Abs(Weekends(i)) + 12 + WeekStart) Mod 7) + 1, Null) arrayW(i) = IIf(arrayW(i) < 1 Or arrayW(i) = 8, Null, arrayW(i)) Next i ElseIf (Int(Weekends) = 1 And Int(Weekends) < 8) Then ReDim arrayW(1) As Variant arrayW(1) = ((Abs(Weekends) + 12 + WeekStart) Mod 7) + 1 arrayW(1) = IIf(arrayW(1) < 1 Or arrayW(1) = 8, Null, arrayW(1)) Else ReDim arrayW(1 To 2) As Variant arrayW(1) = 1 arrayW(2) = 7 End If ' Sort arrayW SelectionSort arrayW ' Replace non-integer values with integers SelectionToInteger arrayW ' Remove double entries and empty elements SelectionUnique arrayW, False Else ' Set 1st element to 0 for 7-workday week ReDim arrayW(1) As Variant arrayW(1) = IIf(Weekends = False, 0, Null) End If ' When empty array, insert default values If arrayW(1) = Null Then ReDim arrayW(1 To 2, 1) As Variant arrayW(1) = 1 arrayW(2) = 7 End If ' Calculate the number of workdays in date interval determined by StartDay and EndDay EnchWorkdaysN = 0 di = Application.WorksheetFunction.Min(StartDate, EndDate) dn = Application.WorksheetFunction.Max(StartDate, EndDate) dx = di Do While dx <= dn x = False i = 1 Do While x = False And i <= UBound(arrayH) And TypeName(arrayH(1)) < "Null" x = (dx = arrayH(i)) i = i + 1 Loop i = 1 Do While x = False And i <= UBound(arrayW) And arrayW(1) < 0 x = (Weekday(dx) = arrayW(i)) i = i + 1 Loop If Not (x) Then EnchWorkdaysN = EnchWorkdaysN + 1 dx = dx + 1 Loop End Function -- Arvi Laanemets ( My real mail address: arvi.laanemets<attarkon.ee ) "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#5
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Hi
Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#6
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Roger,
That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#7
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Thank you, Martin.
Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#8
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Unless I'm missing something, I can't get Rogers or Martins formulas to
work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#9
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
On Mon, 8 Jan 2007 19:10:01 -0800, tamarade
wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? Here is a UDF that should do what you want. It's use is similar to the WORKDAY function except you can define up to four "weekend" days. To enter the UDF, <alt-F11 opens the VB Editor. Ensure your project is highlighted in the Project Explorer window, then Insert/Module and paste the code below into the window that opens. To use this UDF, enter a formula of the type: =wrkday(start_date,num_days,holidays,1,6,7) ======================================= Function NWrkDays(StartDate As Date, EndDate As Date, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Long ' Sunday = 1; Monday = 2; ... Saturday = 7 'credits to Myrna Dim i As Long Dim Count As Long Dim H As Variant Dim w As Long Dim SD As Date, ED As Date Dim DoHolidays As Boolean Dim NegCount As Boolean DoHolidays = Not (Holidays Is Nothing) SD = StartDate: ED = EndDate If SD ED Then SD = EndDate: ED = StartDate NegCount = True End If w = Weekday(SD - 1) For i = SD To ED Count = Count + 1 w = (w Mod 7) + 1 Select Case w Case WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4 Count = Count - 1 Case Else If DoHolidays Then If IsNumeric(Application.Match(i, Holidays, 0)) Then _ Count = Count - 1 End If End Select Next i If NegCount = True Then Count = -Count NWrkDays = Count End Function Function WrkDay(StartDate As Date, ByVal NumDays As Long, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Date ' Sunday = 1; Monday = 2; ... Saturday = 7 Dim i As Long Dim TempDate As Date Dim Stp As Integer Dim NonWrkDays As Long Dim temp As Long, SD As Date, ED As Date Stp = Sgn(NumDays) 'Add NumDays TempDate = StartDate + NumDays 'Add Non-Workdays Do While Abs(NumDays) < temp SD = Application.WorksheetFunction.Min(StartDate + Stp, TempDate) ED = Application.WorksheetFunction.Max(StartDate + Stp, TempDate) temp = NWrkDays(SD, ED, Holidays, WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4) TempDate = TempDate + NumDays - Stp * (temp) Loop WrkDay = TempDate End Function ============================================ --ron |
#10
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Works good, Ron!
I'd still like a worksheet function if ya got one! Biff "Ron Rosenfeld" wrote in message ... On Mon, 8 Jan 2007 19:10:01 -0800, tamarade wrote: I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? Here is a UDF that should do what you want. It's use is similar to the WORKDAY function except you can define up to four "weekend" days. To enter the UDF, <alt-F11 opens the VB Editor. Ensure your project is highlighted in the Project Explorer window, then Insert/Module and paste the code below into the window that opens. To use this UDF, enter a formula of the type: =wrkday(start_date,num_days,holidays,1,6,7) ======================================= Function NWrkDays(StartDate As Date, EndDate As Date, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Long ' Sunday = 1; Monday = 2; ... Saturday = 7 'credits to Myrna Dim i As Long Dim Count As Long Dim H As Variant Dim w As Long Dim SD As Date, ED As Date Dim DoHolidays As Boolean Dim NegCount As Boolean DoHolidays = Not (Holidays Is Nothing) SD = StartDate: ED = EndDate If SD ED Then SD = EndDate: ED = StartDate NegCount = True End If w = Weekday(SD - 1) For i = SD To ED Count = Count + 1 w = (w Mod 7) + 1 Select Case w Case WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4 Count = Count - 1 Case Else If DoHolidays Then If IsNumeric(Application.Match(i, Holidays, 0)) Then _ Count = Count - 1 End If End Select Next i If NegCount = True Then Count = -Count NWrkDays = Count End Function Function WrkDay(StartDate As Date, ByVal NumDays As Long, _ Optional Holidays As Range = Nothing, _ Optional WeekendDay_1 As Integer = 0, _ Optional WeekendDay_2 As Integer = 0, _ Optional WeekendDay_3 As Integer = 0, _ Optional WeekendDay_4 As Integer = 0) As Date ' Sunday = 1; Monday = 2; ... Saturday = 7 Dim i As Long Dim TempDate As Date Dim Stp As Integer Dim NonWrkDays As Long Dim temp As Long, SD As Date, ED As Date Stp = Sgn(NumDays) 'Add NumDays TempDate = StartDate + NumDays 'Add Non-Workdays Do While Abs(NumDays) < temp SD = Application.WorksheetFunction.Min(StartDate + Stp, TempDate) ED = Application.WorksheetFunction.Max(StartDate + Stp, TempDate) temp = NWrkDays(SD, ED, Holidays, WeekendDay_1, WeekendDay_2, WeekendDay_3, WeekendDay_4) TempDate = TempDate + NumDays - Stp * (temp) Loop WrkDay = TempDate End Function ============================================ --ron |
#11
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Just as a matter of completeness as the OP as already accepted the workday
solution is you test if the start day is a Fri/Sat/Sun and report an error. Biff: The method appears to work on my system, please explain the problem. A3=start date and B3 is the nr. of days. Note there is a little bit of disparity as to when it should end is it to include today or not? Anyway a quick fix to weed out incorrect start dates is to test if the start date is =IF(WEEKDAY(A3,2)4,"Error",A3+INT((B3-1)/4)*7+MOD(B3-1,4) +IF(OR(WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)<WEEKDAY(A3,2), WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)4),3,0)) A corresponding change to the macro would also need to be made, but I leave that as an exercise. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "T. Valko" wrote: It still gets tripped up on different scenarios with or without accounting for holidays. Here's a nice test file if you're so inclined. workday.xls 159kb http://cjoint.com/?bkamHyKIF8 Input a start date, duration, add/remove holidays. I still say this is complicated! Biff "Roger Govier" wrote in message ... Hi Biff I can see that you are correct. My quick fix of increasing duration *5/4, doesn't account for completion occurring on a Friday. The following amendment fixes the problem (I think - not thoroughly tested). =IF(WEEKDAY(WORKDAY(Startdate,(Duration*5/4),holidays))=6, WORKDAY(Startdate,(Duration*5/4+1),holidays), WORKDAY(Startdate,(Duration*5/4),holidays) -- Regards Roger Govier "T. Valko" wrote in message ... Unless I'm missing something, I can't get Rogers or Martins formulas to work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#12
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Biff: The method appears to work on my system, please explain the problem.
A3=start date and B3 is the nr. of days. A3 = 1/9/2007 (Tuesday) B3 = 11 Result = 1/25/2007 (Thursday) Correct result should be 1/29/2007 (Monday) Note there is a little bit of disparity as to when it should end is it to include today or not? Workday excludes the start date and includes the end date. Try that test file I posted. It shows which days should be included. Also try Ron's udf. It works under "all scenarios". Biff "Martin Fishlock" wrote in message ... Just as a matter of completeness as the OP as already accepted the workday solution is you test if the start day is a Fri/Sat/Sun and report an error. Biff: The method appears to work on my system, please explain the problem. A3=start date and B3 is the nr. of days. Note there is a little bit of disparity as to when it should end is it to include today or not? Anyway a quick fix to weed out incorrect start dates is to test if the start date is =IF(WEEKDAY(A3,2)4,"Error",A3+INT((B3-1)/4)*7+MOD(B3-1,4) +IF(OR(WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)<WEEKDAY(A3,2), WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)4),3,0)) A corresponding change to the macro would also need to be made, but I leave that as an exercise. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "T. Valko" wrote: It still gets tripped up on different scenarios with or without accounting for holidays. Here's a nice test file if you're so inclined. workday.xls 159kb http://cjoint.com/?bkamHyKIF8 Input a start date, duration, add/remove holidays. I still say this is complicated! Biff "Roger Govier" wrote in message ... Hi Biff I can see that you are correct. My quick fix of increasing duration *5/4, doesn't account for completion occurring on a Friday. The following amendment fixes the problem (I think - not thoroughly tested). =IF(WEEKDAY(WORKDAY(Startdate,(Duration*5/4),holidays))=6, WORKDAY(Startdate,(Duration*5/4+1),holidays), WORKDAY(Startdate,(Duration*5/4),holidays) -- Regards Roger Govier "T. Valko" wrote in message ... Unless I'm missing something, I can't get Rogers or Martins formulas to work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#13
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
It looks like Roger's formula worked for w/o holidays, but got tripped up
because one of the holidays was on a Friday (which is skipped anyway). I thought it worked okay as long as holidays don't have anything that falls on Fri/Sat/Sun. Or is there something I'm missing?? "T. Valko" wrote: It still gets tripped up on different scenarios with or without accounting for holidays. Here's a nice test file if you're so inclined. workday.xls 159kb http://cjoint.com/?bkamHyKIF8 Input a start date, duration, add/remove holidays. I still say this is complicated! Biff "Roger Govier" wrote in message ... Hi Biff I can see that you are correct. My quick fix of increasing duration *5/4, doesn't account for completion occurring on a Friday. The following amendment fixes the problem (I think - not thoroughly tested). =IF(WEEKDAY(WORKDAY(Startdate,(Duration*5/4),holidays))=6, WORKDAY(Startdate,(Duration*5/4+1),holidays), WORKDAY(Startdate,(Duration*5/4),holidays) -- Regards Roger Govier "T. Valko" wrote in message ... Unless I'm missing something, I can't get Rogers or Martins formulas to work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#14
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
I thought it worked okay as long as holidays don't have anything that falls
on Fri/Sat/Sun. Check that. Sat/Sun are okay as Workday takes care of those. Perhaps excluding the holidays that fall on Friday? Just my 2 cents (overpriced perhaps - but since you can't cut a penny in two I rounded up). "JMB" wrote: It looks like Roger's formula worked for w/o holidays, but got tripped up because one of the holidays was on a Friday (which is skipped anyway). I thought it worked okay as long as holidays don't have anything that falls on Fri/Sat/Sun. Or is there something I'm missing?? "T. Valko" wrote: It still gets tripped up on different scenarios with or without accounting for holidays. Here's a nice test file if you're so inclined. workday.xls 159kb http://cjoint.com/?bkamHyKIF8 Input a start date, duration, add/remove holidays. I still say this is complicated! Biff "Roger Govier" wrote in message ... Hi Biff I can see that you are correct. My quick fix of increasing duration *5/4, doesn't account for completion occurring on a Friday. The following amendment fixes the problem (I think - not thoroughly tested). =IF(WEEKDAY(WORKDAY(Startdate,(Duration*5/4),holidays))=6, WORKDAY(Startdate,(Duration*5/4+1),holidays), WORKDAY(Startdate,(Duration*5/4),holidays) -- Regards Roger Govier "T. Valko" wrote in message ... Unless I'm missing something, I can't get Rogers or Martins formulas to work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#15
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Biff,
My assumption was that the start date is inclusive, you don't start the day after the start date. So starting on Tues 9th would finish on the Fri 25th if the time was 11 days. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "T. Valko" wrote: Biff: The method appears to work on my system, please explain the problem. A3=start date and B3 is the nr. of days. A3 = 1/9/2007 (Tuesday) B3 = 11 Result = 1/25/2007 (Thursday) Correct result should be 1/29/2007 (Monday) Note there is a little bit of disparity as to when it should end is it to include today or not? Workday excludes the start date and includes the end date. Try that test file I posted. It shows which days should be included. Also try Ron's udf. It works under "all scenarios". Biff "Martin Fishlock" wrote in message ... Just as a matter of completeness as the OP as already accepted the workday solution is you test if the start day is a Fri/Sat/Sun and report an error. Biff: The method appears to work on my system, please explain the problem. A3=start date and B3 is the nr. of days. Note there is a little bit of disparity as to when it should end is it to include today or not? Anyway a quick fix to weed out incorrect start dates is to test if the start date is =IF(WEEKDAY(A3,2)4,"Error",A3+INT((B3-1)/4)*7+MOD(B3-1,4) +IF(OR(WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)<WEEKDAY(A3,2), WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)4),3,0)) A corresponding change to the macro would also need to be made, but I leave that as an exercise. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "T. Valko" wrote: It still gets tripped up on different scenarios with or without accounting for holidays. Here's a nice test file if you're so inclined. workday.xls 159kb http://cjoint.com/?bkamHyKIF8 Input a start date, duration, add/remove holidays. I still say this is complicated! Biff "Roger Govier" wrote in message ... Hi Biff I can see that you are correct. My quick fix of increasing duration *5/4, doesn't account for completion occurring on a Friday. The following amendment fixes the problem (I think - not thoroughly tested). =IF(WEEKDAY(WORKDAY(Startdate,(Duration*5/4),holidays))=6, WORKDAY(Startdate,(Duration*5/4+1),holidays), WORKDAY(Startdate,(Duration*5/4),holidays) -- Regards Roger Govier "T. Valko" wrote in message ... Unless I'm missing something, I can't get Rogers or Martins formulas to work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#16
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Try this: (without holidays)
Start date = 1/11/2007 (Thursday) Duration = 155 Result = 10/9/2007 (Tuesday) Correct result should be 10/10/2007 (Wednesday) Biff "JMB" wrote in message ... It looks like Roger's formula worked for w/o holidays, but got tripped up because one of the holidays was on a Friday (which is skipped anyway). I thought it worked okay as long as holidays don't have anything that falls on Fri/Sat/Sun. Or is there something I'm missing?? "T. Valko" wrote: It still gets tripped up on different scenarios with or without accounting for holidays. Here's a nice test file if you're so inclined. workday.xls 159kb http://cjoint.com/?bkamHyKIF8 Input a start date, duration, add/remove holidays. I still say this is complicated! Biff "Roger Govier" wrote in message ... Hi Biff I can see that you are correct. My quick fix of increasing duration *5/4, doesn't account for completion occurring on a Friday. The following amendment fixes the problem (I think - not thoroughly tested). =IF(WEEKDAY(WORKDAY(Startdate,(Duration*5/4),holidays))=6, WORKDAY(Startdate,(Duration*5/4+1),holidays), WORKDAY(Startdate,(Duration*5/4),holidays) -- Regards Roger Govier "T. Valko" wrote in message ... Unless I'm missing something, I can't get Rogers or Martins formulas to work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
#17
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
On Tue, 9 Jan 2007 21:50:02 -0500, "T. Valko" wrote:
Works good, Ron! I'd still like a worksheet function if ya got one! Biff I believe Bob Philips has posted a worksheet function solution. But for stuff like this, I find UDF's easier to implement and maintain. --ron |
#18
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
My assumption was that the start date is inclusive
That's not how WORKDAY works. Biff "Martin Fishlock" wrote in message ... Biff, My assumption was that the start date is inclusive, you don't start the day after the start date. So starting on Tues 9th would finish on the Fri 25th if the time was 11 days. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "T. Valko" wrote: Biff: The method appears to work on my system, please explain the problem. A3=start date and B3 is the nr. of days. A3 = 1/9/2007 (Tuesday) B3 = 11 Result = 1/25/2007 (Thursday) Correct result should be 1/29/2007 (Monday) Note there is a little bit of disparity as to when it should end is it to include today or not? Workday excludes the start date and includes the end date. Try that test file I posted. It shows which days should be included. Also try Ron's udf. It works under "all scenarios". Biff "Martin Fishlock" wrote in message ... Just as a matter of completeness as the OP as already accepted the workday solution is you test if the start day is a Fri/Sat/Sun and report an error. Biff: The method appears to work on my system, please explain the problem. A3=start date and B3 is the nr. of days. Note there is a little bit of disparity as to when it should end is it to include today or not? Anyway a quick fix to weed out incorrect start dates is to test if the start date is =IF(WEEKDAY(A3,2)4,"Error",A3+INT((B3-1)/4)*7+MOD(B3-1,4) +IF(OR(WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)<WEEKDAY(A3,2), WEEKDAY(A3+INT((B3-1)/4)*7 +MOD(B3-1,4),2)4),3,0)) A corresponding change to the macro would also need to be made, but I leave that as an exercise. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "T. Valko" wrote: It still gets tripped up on different scenarios with or without accounting for holidays. Here's a nice test file if you're so inclined. workday.xls 159kb http://cjoint.com/?bkamHyKIF8 Input a start date, duration, add/remove holidays. I still say this is complicated! Biff "Roger Govier" wrote in message ... Hi Biff I can see that you are correct. My quick fix of increasing duration *5/4, doesn't account for completion occurring on a Friday. The following amendment fixes the problem (I think - not thoroughly tested). =IF(WEEKDAY(WORKDAY(Startdate,(Duration*5/4),holidays))=6, WORKDAY(Startdate,(Duration*5/4+1),holidays), WORKDAY(Startdate,(Duration*5/4),holidays) -- Regards Roger Govier "T. Valko" wrote in message ... Unless I'm missing something, I can't get Rogers or Martins formulas to work. Start date = 1/9/2007 (Tuesday Jan 9 2007) Days = 11 Roger = 1/26/2007 (Friday Jan 26 2007) Martin = 1/25/2007 (Thursday Jan 25 2007) I believe the correct result should be 1/29/2007 (Monday Jan 29 2007) I think this is much more complicated than it appears on the surface. After about an hour of tinkering I haven't come up with anything that works *under all circumstances*. JMB's suggestion works but listing all Fridays as holidays may not be very desirable. I haven't tried Arvi's udf. Biff "Roger Govier" wrote in message ... Thank you, Martin. Much appreciated and Happy New Year. -- Regards Roger Govier "Martin Fishlock" wrote in message ... Roger, That's a nice solution to the problem. -- Hope this helps Martin Fishlock, Bangkok, Thailand Please do not forget to rate this reply. "Roger Govier" wrote: Hi Provided you have ToolsAddinsAnalysis Toolpack selected, then you could modify the Workday function. =WORKDAY(Startdate,(Duration*5/4),holidays) where holidays is a named range of holiday dates or a range of cells e.g. $C$1:$C$9 containing the holiday dates. Multiplying your duration by 5/4 will account for a 4 day week. -- Regards Roger Govier "tamarade" wrote in message ... I am trying to create a formula that will result in a date. I have a start date, a number of work days, however my dilemna is we only work 4 days. So the formula would have to compute a completion date but exclude Fri, sat, & sunday, any suggestions? |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Reusing formula | Excel Discussion (Misc queries) | |||
formula problem | Excel Worksheet Functions | |||
Wrong Week number | Excel Worksheet Functions | |||
Work Rota - Do I need a formula? | Excel Discussion (Misc queries) | |||
4 Day Work Week in a formula | Excel Discussion (Misc queries) |