Hi
as stated: You have to install the Analysis Toolpak Addin (goto 'Tools-
Addins' and tick this addin)
--
Regards
Frank Kabel
Frankfurt, Germany
"CNGracin" schrieb im Newsbeitrag
...
Thank you for the quick response... but that returned a invalid name
error.
"Frank Kabel" wrote:
Hi
=WORKDAY(C2,-3)
Note: The Analysis Toolpak Addin must be installed for this
--
Regards
Frank Kabel
Frankfurt, Germany
"CNGracin" schrieb im Newsbeitrag
...
What I would like to be able to do in MS Excel (2002) is this and
I€„¢m
not
sure if it€„¢s possible. How would I take a date field in Excel
and
decrease
that date by three BUSINESS days? I€„¢m filling in the blanks on
a large
roll-out schedule and would rather not if possible manually calculate
several
hundred dates.
Example:
The first final date of completion for the project would be Monday
1/17/2005. This date appears in cell C2.
I need to show on a schedule that three business days before there will
be
an installation visit. The result would be Wednesday 1/12/04. This
would
appear in cell B2.
Is there a valid expression for =C2 €€œ (3 business day?)
|