Default Formula for a 4 day work week

Thank you, Martin.
Much appreciated and Happy New Year.

--
Regards

Roger Govier


"Martin Fishlock" wrote in message
...
Roger,

That's a nice solution to the problem.
--
Hope this helps
Martin Fishlock, Bangkok, Thailand
Please do not forget to rate this reply.


"Roger Govier" wrote:

Hi

Provided you have ToolsAddinsAnalysis Toolpack selected, then you
could modify the Workday function.

=WORKDAY(Startdate,(Duration*5/4),holidays)
where holidays is a named range of holiday dates or a range of cells
e.g. $C$1:$C$9 containing the holiday dates.

Multiplying your duration by 5/4 will account for a 4 day week.

--
Regards

Roger Govier


"tamarade" wrote in message
...
I am trying to create a formula that will result in a date. I have
a
start
date, a number of work days, however my dilemna is we only work 4
days. So
the formula would have to compute a completion date but exclude
Fri,
sat, &
sunday, any suggestions?