Calculate Start Dates based on Need-By Date?
Since 6 weeks = 42 days, just subtract 42.
=B30-42
HTH,
Elkar
"GB" wrote:
I'm trying to calculate a start date based on a "need by" date.
For instance.....cell B30 in a worksheet has a "need by" date of 5/4/2006.
This date means I have to "start" the project 6 weeks before that.
I'd like the formula to back-calculate the "start" date based on the "need
by" date.
I've tried using EDATE but get a "#NAME" error. I've tried =DATE92006,5,4)
for the "need by" date but it still won't calculate backwards.
Any help would be appreciated.
Thanks a lot!
|