Calculate A Date Excluding Weekends And Holidays
I have a date and a series of tasks that need to be completed by a certain number of days from the intial date. The time to complete the tasks can not include weekends or holidays. Example: Initial date is 2/15/2006 I have 10 business days to complete a task All Help will be appreciated. Thank you. -- travelersway ------------------------------------------------------------------------ travelersway's Profile: http://www.excelforum.com/member.php...o&userid=17623 View this thread: http://www.excelforum.com/showthread...hreadid=510028 |
#2
Posted to microsoft.public.excel.newusers
|
|||
|
|||
Calculate A Date Excluding Weekends And Holidays
A good starting place for information is here -
http://www.cpearson.com/excel/DateTimeWS.htm "travelersway" wrote: I have a date and a series of tasks that need to be completed by a certain number of days from the intial date. The time to complete the tasks can not include weekends or holidays. Example: Initial date is 2/15/2006 I have 10 business days to complete a task All Help will be appreciated. Thank you. -- travelersway ------------------------------------------------------------------------ travelersway's Profile: http://www.excelforum.com/member.php...o&userid=17623 View this thread: http://www.excelforum.com/showthread...hreadid=510028 |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Formula for adding days to a date excluding weekends and holidays? | Excel Discussion (Misc queries) | |||
Workday With Weekends Excluding Holidays | Excel Worksheet Functions | |||
Calculate difference between 2 date and times with average | Excel Discussion (Misc queries) | |||
How do you count work days excluding weekends and holidays? | Excel Discussion (Misc queries) | |||
Formula - Excluding weekends & holidays | Excel Worksheet Functions |