I have a spread sheet used for production planning which predicts the finsh time of a job depending on its duration. This works fine but I now have the problem that production is no longer 24 hours so if a 12 hour job starts at 15:00, no work will be done between 21:00 and 06:00 (9 hours) so it will finish at 12:00 noon on the following day.
Is there a formula that will add 9 hours to the duration if the calculated finish time falls during the night shift?

Thanks in anticipation
Martin
  #2   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 8,651
Default calculate finishing time if night shift aren't working

If your start time is in A2, duration in B2, night shift start time in C$2, night shift finish time in D$2:
Finish time would be =A2+B2+IF(A2+B2C$2,MOD(D$2-C$2,1))
--
David Biddulph

"Martin B" wrote in message ...
I have a spread sheet used for production planning which predicts the finsh time of a job depending on its duration. This works fine but I now have the problem that production is no longer 24 hours so if a 12 hour job starts at 15:00, no work will be done between 21:00 and 06:00 (9 hours) so it will finish at 12:00 noon on the following day.
Is there a formula that will add 9 hours to the duration if the calculated finish time falls during the night shift?

Thanks in anticipation
Martin
Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculate Total hours worked during workdays within given shift time. noname Excel Discussion (Misc queries) 2 April 8th 07 06:28 PM
Adding a decimal hours to a starting time to give a finishing tim Peter Rooney Excel Discussion (Misc queries) 3 March 21st 07 02:48 PM
Calculate working hours from a start and finish time over several Jive Excel Worksheet Functions 1 September 25th 06 12:46 PM
Working night and day..... Timesheet Kjaltrik Excel Worksheet Functions 5 September 19th 06 08:36 PM
How do I write an Excel formula to calculate my working time? GregJ Excel Worksheet Functions 3 December 27th 05 02:48 PM


All times are GMT +1. The time now is 10:41 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"