Hi all

I need to ascertain when a given action needs to be completed by, by
adding a SLA (service level agreement) to the current date and time.

Note:
- SLAs may be anything from 1 minute to 2 weeks
- Weekends must be ignored (not included in calcs)
- A work day is Monday to Friday 6.30AM to 7.00PM

So, for example, if it's Friday 4PM and a SLA is 4 hours, the required
completion time should be Monday 7.30AM.

I've looked at Chip Pearson's site for date/time calculation, but my
problem does not appear to be addressed. Any direction is much
appreciated.

Paul Martin
Melbourne, Australia
  #2   Report Post  
Bob Phillips
 
Posts: n/a
Default

Paul,

Try this (I have given it a test, but your data is bound to be better)

Assuming the incident date/time in A2 such as dd/mm/yyyy hh:mm:ss, and the
SLA time in B1 in hours (make sure this is formatted as [h]:mm to allow
more than 1 day), e.g. 04:00, 48:)0, then in B2

=IF(DAY($A2+B$1)=DAY($A2),$A2+B$1,$A2+B$1+(WORKDAY ($A2,1)-INT($A2)-1))


--

HTH

RP
(remove nothere from the email address if mailing direct)


"Paul Martin" wrote in message
om...
Hi all

I need to ascertain when a given action needs to be completed by, by
adding a SLA (service level agreement) to the current date and time.

Note:
- SLAs may be anything from 1 minute to 2 weeks
- Weekends must be ignored (not included in calcs)
- A work day is Monday to Friday 6.30AM to 7.00PM

So, for example, if it's Friday 4PM and a SLA is 4 hours, the required
completion time should be Monday 7.30AM.

I've looked at Chip Pearson's site for date/time calculation, but my
problem does not appear to be addressed. Any direction is much
appreciated.

Paul Martin
Melbourne, Australia



Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
How To Refresh Chart Data Without Calculating The Worksheet Carl Bowman Charts and Charting in Excel 5 January 19th 05 09:28 PM
Calculating Interest where rate changes per quarter Dean Strudwick Excel Discussion (Misc queries) 1 December 6th 04 11:36 PM
Calculating tax Formula DWright Excel Discussion (Misc queries) 7 December 1st 04 07:37 AM
Formulas stop calculating at random times when editing a few spreadsheets. Luke MacNeil Excel Discussion (Misc queries) 3 November 30th 04 03:21 PM
Calculating without including Hidden Cells LiquidFire Excel Discussion (Misc queries) 3 November 29th 04 08:35 PM


All times are GMT +1. The time now is 06:45 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"